Adjudication and the Defective Premises Act

BDW Trading Ltd v Ardmore Construction Ltd [2024] EWHC 3235 (TCC): A Landmark Decision on Adjudication and the Defective Premises Act 1972

The High Court’s recent decision in BDW Trading Ltd v Ardmore Construction Ltd [2024] EWHC 3235 (TCC) has confirmed, for the first time, that adjudication can be used to determine claims under the Defective Premises Act 1972 (DPA). This ruling significantly impacts the construction industry by extending the scope of adjudication to statutory claims, particularly those benefiting from the extended limitation periods introduced by the Building Safety Act 2022 (BSA).

Background to the Case

BDW Trading Ltd, a major residential developer, engaged Ardmore Construction Ltd to carry out construction works on a residential project. Following completion, BDW alleged that serious defects existed in the works, rendering the premises unfit for habitation, thereby giving rise to a claim under the DPA.

The claim was brought against Ardmore under the newly extended limitation period introduced by the BSA, which retrospectively extended the limitation period for claims under the DPA from six to thirty years for works completed before 28 June 2022, and to fifteen years for works completed thereafter. BDW opted to refer the dispute to adjudication, seeking a quick and cost-effective resolution.

Ardmore resisted adjudication, arguing that statutory claims under the DPA fell outside the scope of adjudication, which traditionally applies to contractual disputes under the Housing Grants, Construction and Regeneration Act 1996 (HGCRA). This jurisdictional challenge led to BDW seeking enforcement of the adjudicator’s decision in the Technology and Construction Court (TCC).

Key Issues Before the Court

The central issue in BDW Trading Ltd v Ardmore was whether an adjudicator had jurisdiction to determine claims under the DPA, a statutory rather than contractual cause of action. The court was required to consider:

  • Whether claims under the DPA qualify as “disputes” within the meaning of the HGCRA, thereby falling within the scope of adjudication.
  • Whether the extended limitation period under the BSA impacts the enforceability of adjudication decisions involving DPA claims.
  • Whether adjudication provides an appropriate mechanism for resolving claims concerning statutory duties.

The High Court’s Decision

The TCC ruled in favour of BDW Trading Ltd, holding that:

  • DPA Claims Are Subject to Adjudication: The court found that adjudication is not limited to contractual disputes but extends to statutory claims that arise in the context of construction contracts. The judgment emphasised that the DPA imposes a statutory duty on parties involved in construction projects, and disputes regarding compliance with this duty fall within the scope of adjudication under the HGCRA.
  • The Extended Limitation Period Under the BSA Applies: The court confirmed that the retrospective and prospective extension of limitation periods under the BSA does not preclude adjudication as a method of dispute resolution. Adjudication remains a viable means of determining liability under the DPA, even for claims arising from projects completed decades ago.
  • Adjudication as an Effective Dispute Resolution Mechanism: The court acknowledged the practical benefits of adjudication, including speed and cost-effectiveness. It noted that restricting adjudication to purely contractual disputes would undermine its utility in resolving construction-related issues efficiently.

Implications for the Construction Industry

The ruling in BDW Trading Ltd v Ardmore has far-reaching consequences for contractors, developers, and other construction stakeholders:

  • Wider Use of Adjudication: The decision clarifies that parties can use adjudication to resolve disputes under the DPA, offering a faster and less costly alternative to litigation.
  • Increased Exposure for Contractors: With the extended limitation periods under the BSA, contractors and developers could now face claims for defective premises decades after completion, and these claims can be adjudicated.
  • Potential Increase in Adjudications: The decision is likely to lead to an increase in adjudications involving DPA claims, compelling contractors to be more diligent in their record-keeping and risk management.
  • Greater Certainty in Dispute Resolution: The confirmation that statutory claims under the DPA can be adjudicated provides clarity on the use of adjudication for non-contractual claims, ensuring that parties can rely on this mechanism for a wide range of disputes.

Conclusion

The High Court’s decision in BDW Trading Ltd v Ardmore Construction Ltd marks a significant development in construction law by confirming that adjudication can be used to resolve claims under the DPA. The case establishes that adjudication is not confined to contractual disputes but extends to statutory claims where appropriate. With the extended limitation periods under the BSA now in effect, construction professionals must be prepared for an increased volume of adjudications concerning historical defects. This ruling reinforces adjudication as a powerful tool for resolving construction disputes efficiently and cost-effectively, setting a crucial precedent for future cases.